The Missing Ingredient That Sank a $1.2 Million Construction Lien: Cuevas Machine Company, Inc. v. Calgon Carbon Corporation
On October 15, 2026, the Mississippi Supreme Court issued a decision that bears directly on the enforceability of construction liens in Mississippi. In Cuevas Machine Company, Inc. v. Calgon Carbon Corp., it held that a construction lien that does not clearly state the last date work was performed cannot be enforced, even if the claimant attaches dated invoices.